EEE JV: automation design for 35–150 kV substations
Telemetry, data acquisition and transmission, communications and dispatch control in substation upgrade projects — from Savino substation to Khrabrovo airport.
| Years | 2010–2014 |
|---|---|
| Client | EEE Energy Ecology Engineering JV and partner design firms; end clients — regional grid companies, Russian Railways, Khrabrovo airport |
| Location | St Petersburg, Novgorod and Irkutsk regions, Murmansk, Kaliningrad |
| Role | Designer of automation and telemetry sections (contract) |
Challenge
When a substation is upgraded, the general designer produces the electrical part, while the automation section — telemetry, data acquisition and transmission, process control, communications, metering, video surveillance — must connect the new equipment to the dispatch centres of the grid company and the System Operator under their technical conditions.
Solution
Savino 110/10 kV (2010): telemetry on Telekanal-M2 devices and KIPP-2M meters on a shared Ethernet network, IEC 60870-5-104 to the control centre, D-Link DES-3526 switches stacked in a 1 Gbit/s fibre ring, telemetry cabinets in the 10 kV switchgear, and terminal blocks as the boundary with protection. OL-130 (2011): a VBP-110 110 kV breaker with a TOR-200 relay, telemetry, communications, metering and video sections, a 110 kV sectioning point. Irkutsk (2011): data acquisition systems for Lenino 35/6 kV and Tsentralnaya 110/10/6 kV. Lavna-Traction 150 kV (2013, Murmansk transport hub): dispatch control and telemetry to the Kola regional dispatch centre — ENIP-2 multifunction transducers, ENMV indication modules, Modbus/IEC 60870-5-104 gateways, time sync, operator workstations, requirements for adjacent systems. Khrabrovo airport (2013–2014): technical conditions for dispatch control and metering of the airfield power supply.
My part
Explanatory notes and structural diagrams, telemetry lists and volumes, communication-channel specifications, equipment lists and costings, responses to expert review.
Outcome
Automation design packages for 35–150 kV substations in five regions, agreed with grid companies and the System Operator.